Ian has more than fifteen years of experience in the construction and claims industry as project engineer, planning engineer and project control manager, of which, Ian has spent nine years as a forensic planning engineer and acting as a named delay expert in dispute resolution and litigation proceedings. 

Expert Commissions 

Refurbishment of Overhead Transmission Line, UK

​Instructed by solicitors under Part 35 CPR to provide an independent expert opinion for the High Court of Justice of the Defendant’s counterclaim for losses incurred on the Project due to alleged defective conductor supplied by the manufacturer.

​Construction of a Twenty-Seven High Rise Building, Botswana

​Instructed by solicitors to provide an independent expert opinion in arbitration proceedings on the likely causes of critical delay to the Works and assessment of the claimants alleged critical delay events.

​Construction of Moin Terminal, Costa Rica

​Instructed by the Employer to provide an independent expert opinion for DAB proceedings on the critical delays to the Project’s contractual milestones and the likely causes of those critical delays.  

Modernisation of the Callao North Terminal, Peru

​Instructed by the Responding Party in DAB proceedings to provide an independent expert opinion on the Referring party’s delay expert report.  

​Refurbishment of 2 Soho Square, UK

​Instructed by solicitors to provide a Part 35 CPR opinion in adjudication proceedings on the likely causes of critical delay to the Works and assessment of the claimants alleged critical delay events.

Widening Seaforth Passage, UK

​Instructed by the sub-subcontractor, on behalf of the Main Contractor, to provide an independent expert opinion for adjudication as to the delaying effects of alleged Employer delay events had on the Completion Date during the demolition works of the quay side.

 